FCC Rationalization (2016)

Sep 2016 – Oct 2016

  • Facilitated alarm rationalization efforts for mission-critical Fluid Catalytic Cracker (FCC) unit at the company’s flagship 380,000 bpd refinery.
  • Rationalized DCS and SIS systems on this unit to corporate standards.
  • Coached project team on best-practices for alarm rationalization.
  • Provided guidance on implementation of rationalization design to control systems.

 

SAGD Rationalization (2016)

May 2016 – Jul 2016

Alarm rationalization for greenfield SAGD Central Plant & Wellpads. Completed on schedule and on budget with multiple scope changes for additional work. Averaged 105 tags /d.
  • Facilitated alarm rationalization efforts for multiple plant areas in greenfield SAGD thermal extraction facility.
  • Coached project team on best-practices for alarm rationalization.
  • Provided guidance on implementation of rationalization design to control systems.